All posts in Moffat Tunnel

01Mar

March 1926 at the Moffat Tunnel: Delay, Doubt, and Death

In Moffat Tunnel by Preserve Rollins Pass / March 1, 2026 / Comments are closed

In March 1926 at the Moffat Tunnel, thirty days of water stalled the headings, the city’s faith in the project faltered, and the cost of the work could no longer be treated as abstract.

Moffat Tunnel Construction Happenings from 100 Years Ago

March 1926 was the month when the Moffat Tunnel looked numerically close and operationally fragile at the same time—a combination that can be more dangerous than being obviously far from the finish line. Early in the month, officials said the two main headings were separated by only 5,568 feet. Progress, when reduced to percentages, sounded almost like a victory lap: the water tunnel and the main headings at 85 percent complete, crosscuts at 88 percent, and the enlargement of the full-size railroad bore at 56 percent. Yet the same reporting carried a sobering counterweight. As the remaining distance shrank into “mere thousands of feet,” the mountain was proving more unpredictable than at any earlier stage.

The month’s defining setback began with a single blasting round the night of February 28 into March 1 in the water tunnel, when the shot broke abruptly into an underground stream. At first, the inflow was estimated at roughly 3,000 gallons per minute, later described as settling nearer 1,500. The more consequential detail was not the early peak but the persistence. A report published March 31 stated the flow had continued “unabated for 30 days,” which meant March unfolded under a constant hydraulic burden rather than a short-lived incident. Earlier water strikes in the tunnel, it was emphasized, had typically dwindled within a few days. This one did not. That difference in behavior mattered because it shifted the problem from an emergency to a condition—something crews had to live with, work around, and pay for, day after day.

The trouble was concentrated at the East Portal, and geography made it worse at precisely the wrong moment. By then, the east-side heading had crossed the apex and was driving downgrade toward the west. Under ordinary circumstances at the Moffat Tunnel, gravity is a quiet ally: water tends to find its way out of a tunnel toward daylight. Here, gravity became the opponent. Instead of draining out, the water backed into the workings, flooding headings, overwhelming the pumps that were already in place, and forcing workers to remove machinery before it disappeared under rising water. In a project built on planning and repetition, this was the kind of reversal that punishes assumptions. The heading was not merely wet; it was in the wrong position to shed water without sustained mechanical effort.

Engineers tried to quantify the scale of the problem in a way the public could grasp. They estimated that 67,320,000 gallons (modern day note: this amount of water could fill ~102 Olympic-size swimming pools) had poured through during the first month alone. They also reached a conclusion that sounded technical but carried practical dread: they believed the water was Western Slope water traveling eastward. They called it the least favorable hydraulic condition they could imagine. The phrase did not mean water was “bad” in the abstract. It meant the source appeared capable of feeding the bore persistently from the far side of the Divide, making it harder to expect a natural tapering or an easy relief through drainage.

Water, however, was only part of the mechanism. The blast did not merely open a clean conduit; it broke into crushed, running material—“ground-up rock… like cement.” Tons of this muck poured into the heading along with the inflow, burying the work and halting progress for extended periods. That detail changes the picture. Flooding is one kind of disruption. Flooding combined with unstable, self-feeding debris becomes something else entirely: a cycle in which clearing the face does not reliably create progress, because the face can refill. In that environment, “advance” is not a simple matter of more men or longer shifts. It becomes a contest between excavation and re-accumulation.

The response was an exercise in containment rather than cure. Pumps were brought up and kept running, and the water had to be forced up to the apex so it could then drain for miles to the portal. A weir was built to measure the flow, because a project cannot manage what it cannot measure, and earlier experience was no longer a trustworthy guide. To regain control at the source, a drift was driven from the pioneer bore—forty to fifty feet ahead of the railroad heading—to crosscut the vein. Blocking the flow entirely remained under discussion, which is another way of acknowledging that the problem did not present a single obvious remedy. In March, the East Portal was not “behind schedule” so much as locked in a tactical struggle where each option carried costs, uncertainties, and consequences that could not be wished away.

Conditions on the West Portal offered no comfort. That side was described as a “veritable hoodoo,” a phrase that reads like gallows humor from people forced to keep working where the ground refuses to behave. Timbering was relentless, and the accounts stressed that nearly every foot required support. Heavy steel beams were installed in places to restrain slipping walls. Engineers projected more than nine million feet of timber—much of it Oregon fir—would be needed before unstable sections could be secured. March thus became a month of two simultaneous fights: at one end, water and running muck; at the other, ground that demanded timber and steel simply to remain in place long enough for the work to continue.

Even with the East Portal slowed to “practically a standstill” for about a month, officials insisted the project remained about five months ahead of schedule. That claim carried its own pressure. To hole through in July, the accounts said the headings would need to average forty feet of daily progress once normal work resumed. That number matters because it reveals how narrow the margin could become once trouble arrived. A schedule can absorb setbacks when it has slack. A schedule that requires an aggressive daily average turns recovery into a separate risk—one that can tempt corners to be cut, judgment to be rushed, and safety procedures to become “flexible” under the weight of public expectation.

Labor scaled accordingly. The workforce rose to roughly 600 men, the largest since construction began. Supervisors were quoted acknowledging that younger miners were preferred for the hardest assignments because they could better withstand smoke and the conditions inside the mountain. The statement is plain, even clinical, yet it exposes a reality that polite progress reports can conceal: endurance itself had become part of the project’s calculus. March was not only a matter of engineering quantities—feet, gallons, timbers—but of how long nerve and sinew could keep functioning inside an environment that was cold, dark, wet, loud, and increasingly unforgiving.

Amid the flood and the timber, the human cost of the work returned to the foreground in the death of Charles Cecil “Charley” Decker, almost certainly eighteen, though some newspapers misstated his age. A mucker at the West Portal for only about a month, he was struck by a slab of roof rock after a blasting round. The reports emphasized that he entered before loose material had been fully scaled. The slab hit with enough force to break ribs, leg, pelvic bone, and back, and to cause catastrophic internal injuries. He was taken to the West Portal hospital, and from the outset his condition was described as hopeless. He lived nearly a day—long enough for his parents to reach him—before dying.

The tributes that followed were not generic. They were specific in a way that suggests a community trying to explain, to itself, why this loss felt so sharply personal. Decker was described as physically strong and unusually upright—“morally clean,” a boy who “stood out from among boys.” One line captured the kind of memory that refuses to be reduced to an accident report: “his smile will always remain with us.” Funeral services in Yampa drew a wide circle of relatives, neighbors, and lifelong friends. Local young men served as pallbearers. Musical tributes were offered. He was buried in Yampa cemetery, mourned by his parents, four surviving brothers, and his grandmother. Newspapers wrote that his death cast “a deep gloom” across the region because he was just entering early manhood and was held in universal esteem. In March 1926, the tunnel’s progress could be counted in feet, but its cost was being counted in names.

While crews fought geology underground, Denver fought politics above it, and March reads like the moment the project’s civic narrative began to fracture under its own weight. As financial and governance realities became harder to soften with optimism, newspapers began to speak in a different register. One blunt line framed the shift in public mood: “Gradually it seems to be dawning on Denver that their Moffat Tunnel is going to be the very biggest white elephant they ever purchased.” That language was not merely colorful. It signaled a fear that the tunnel was becoming a permanent obligation rather than a triumphant public work—an asset that would demand continual explanation, continual funding, and continual defense.

Much of the dispute focused on structure: who held risk, who controlled decisions, and who would be forced to pay when nature imposed costs beyond anyone’s preference. Critics hammered on the idea that Denver owned the overwhelming share of the enterprise and would bear the same share of any losses, whether the bookkeeping ran through the tunnel district or the water system. The point was framed as an uncomfortable inevitability: it could “look like a difference over a matter of bookkeeping,” yet still end with the same payer, in roughly the same proportion, regardless of which political faction prevailed in the argument.

City Attorney Henry May pressed the legal vulnerability of the arrangements with language that invited skepticism rather than deference. He called the structure “full of flaws and of at least doubtful validity,” then framed the question that makes any open-ended public commitment feel intolerable: if supplemental bonds could be issued, “how do we know what amount of bonds will be issued?” He also pointed to the absence of a reporting requirement—“no provision… requiring the commission to report to anyone” how or when money was to be spent. The attack landed not only because it questioned a policy choice, but also because it questioned the presence of guardrails. In public finance, distrust tends to metastasize fastest where oversight feels optional.

Liability anxieties attached themselves to the water bore in particular, and that is where technical misunderstanding became political fuel. Critics seized on the claim that the water tunnel was placed “above” the railroad tunnel, then asked a question designed to sound like common sense: “Why was the water tunnel placed above the railroad tunnel? Everyone knows that water usually runs downward, and not up.” As an engineering premise, the “directly overhead” framing is not consistent with the side-by-side configuration described in the material at hand, but politically the claim did not need to be geometrically perfect to be damaging. It needed only to feel plausible long enough to harden suspicion. The result was a public argument in which the same words—“leaks,” “percolations,” “damage”—could be used to frame the commission as careless, evasive, or both.

The political consequences arrived quickly and personally. A headline described a “brutal attack on water commissioners” that caused three men to resign, calling them “able and high-minded,” and noting that the mayor had difficulty finding replacements with comparable ability. That detail matters because governance capacity is not infinite. When qualified people walk away, the institution loses competence at the moment it most needs steadiness. The dispute thus threatened not only the tunnel’s reputation but the practical quality of decision-making while the project remained exposed to geological surprises.

By late March, even former boosters were framed as conceding that Denver was trapped by its own stake. One line summed up the predicament with coarse directness: “Denver is in a hel-uv-a-fix. For she must eventually extinguish 85% of the cost of the big bore whether she wishes to or not.” Another remark, steeped in fatalism, pointed to “years of litigation and trouble” and the chorus of “I told you so.” The press, in this portrayal, was not merely reporting disagreement. It was documenting a civic mood shifting from optimism to suspicion, from pride to anxiety, and from “when will it be finished” to “what have we committed ourselves to, and who will be accountable if it goes wrong.”

Yet March also contained an impulse to stabilize meaning before events stabilized on their own. An “official history” of the tunnel—written by Edgar McMechen and to be issued by Wahlgren Publishing—was endorsed by the Denver Chamber of Commerce directors, after earlier endorsement by the commission. The move reads like an attempt to consolidate legitimacy at a moment when legitimacy was fraying. In a large public enterprise, narrative becomes a form of governance. When the ground turns wet, and politics turns hot, whoever controls the frame can influence whether the next setback is treated as an unfortunate chapter in a heroic story or as proof that the entire undertaking was flawed from the start.

That was March 1926 in its clearest shape: measurable proximity to completion, paired with conditions that made completion feel less assured; mechanical persistence underground, paired with institutional instability above it; and a community’s grief for one young man, paired with a city’s fear that the costs—financial, legal, and moral—were only beginning to come due.

Water fills the pioneer bore beneath the Continental Divide, illuminating the relentless groundwater inflows that complicated excavation efforts during the construction of the Moffat Tunnel.
A granite headstone marks the final resting place for Charley Decker in Yampa, Colorado. The authors were honored to speak with Verna Decker Whaley for her recollections of family stories about Charley. Charley’s tombstone can be found in the South Routt Cemetery at Section 4, Lot 78, Plot 4. Read more about our efforts to restore these fallen workers to the historical record.

B. Travis Wright, MPS | Preserve Rollins Pass | March 1, 2026

The primary purpose of our work is to inform the public.

26Feb

The Moffat Tunnel Opening Date: The First Train Ran in 1928, 98 Years Ago

In Moffat Tunnel by Preserve Rollins Pass / February 26, 2026 / Comments are closed

When was the Moffat Tunnel opening date? It depends on whether you’re holding a drill bit, a golden telegraph key, or a train schedule.

• Saturday, February 12, 1927 — The pioneer bore was first holed through with a three-inch drill, establishing contact between East and West Portal.
• Friday, February 18, 1927 — President Calvin Coolidge, from Washington, ceremonially blasted the final rock of the pioneer bore by touching a golden telegraph key, symbolically completing the connection.
• Friday, July 8, 1927 — The main railroad bore was holed through “shortly before” 2 p.m. near Crosscut No. 9. This connected the two sides in full, though months of enlargement and finishing work still remained before the tunnel was usable for rail traffic.
• Saturday, December 10, 1927 — The final charges of dynamite were fired in the railroad tunnel, opening it to full size. Still remaining: concreting, equipment removal, and laying track.
• Tuesday, February 7, 1928 — Standard-gauge track through the Moffat Tunnel was officially completed, just under three weeks before what would become opening day. Work could not begin until the week of January 15, when crews first removed the temporary narrow-gauge rails that had carried muck cars and other construction equipment.

In project terms, these were successive construction milestones, each advancing the tunnel from excavation to full operation. Completion depends on which milestone one recognizes as decisive:

If you’re an engineer — February 12.
If you’re a president — February 18.
If you’re a construction superintendent — July 8.
If you’re a powderman — December 10.
If you’re a railroad — February 7.

If you’re waiting for the first official train? Pack your bags for February 26, 1928.

Ninety-eight years ago this week, David Moffat’s dream became operational reality. A train ran beneath the Continental Divide—but the path to that moment was neither singular nor simple. If you’ve followed our month-by-month account of the Moffat Tunnel’s construction over the past several years, you know the work was anything but straightforward, and we are nearing the most difficult phase. Ahead lie stalled headings and collapsing ground, heartbreaking fatalities, flashes of raw heroism for a friend, a small life saved through the newly pierced pioneer bore, a blacksmith shop fire in the dead of winter that threatened an entire camp, and the long grind that turned blasted rock into a reliable route. Even the bronze “1927” on the portals has its own subtle history. Early photographs seem to tell a slightly different story—one we’ll examine next year.

A century ago, crews were enduring some of the harshest conditions of the entire undertaking. Two years remain before the 1928 centennial of the first train. Join us as we continue telling the full story behind one of the most consequential American engineering achievements of its era and how the tunnel was won.

Temporary rails and standing water inside the Moffat Tunnel prior to the official Moffat Tunnel opening date in February 1928.

B. Travis Wright, MPS | Preserve Rollins Pass | February 26, 2026

The primary purpose of our work is to inform the public.

04Feb

The Moffat Tunnel in February 1926: Four-Fifths Through the Mountain, Never Free of the Cost

In Moffat Tunnel by Preserve Rollins Pass / February 4, 2026 / Comments are closed

February 1926 was the month the Moffat Tunnel clawed its way deeper under the Divide; the mountain reminded everyone it wasn’t giving up the fight for free.

Moffat Tunnel Construction Happenings from 100 Years Ago

By February 1926, the Moffat Tunnel had advanced to a threshold moment that felt both triumphant and unfinished. The Commission’s progress report dated February 1 stated that the main headings of both the railroad tunnel and the parallel water tunnel were now roughly four-fifths driven under James Peak. Nearly 26,000 feet of heading had been excavated from the two portals combined, leaving about 6,500 feet before the mountain would finally give way and the headings meet. Yet this was progress measured in narrow terms. Enlargement of the railroad bore—shaping the heading into a full-size operational tunnel—lagged far behind. Just over 17,000 feet had been widened to final dimensions, slightly more than half the length of the bore. The project’s two ends told different stories: excessive water that had plagued the East Portal was finally under control, while firmer rock in the west allowed the work to proceed with less timbering at daily rates as high as twenty to twenty-five feet. Engineers sounded cautiously confident that holing through could occur later in the year. Still, everyone understood that “holing through” was only one milestone on a much longer road to completion.

Even as miners carved into the heart of the mountain, the West Portal continued to function as an established community rather than a temporary work camp. Newspaper accounts describe active fraternal life at the site, including Elks initiations held in a recreation hall large enough for ritual ceremonies and a banquet space capable of feeding nearly ninety people. The lodge itself counted at least forty-five members. Corporate leadership did not stand apart from this social world. George Lewis, identified as the tunnel’s general manager, presided as toastmaster, a detail that illustrates how fully management and community overlapped at West Portal. The gatherings stretched late into the night, with attendees not departing until after 2:40 a.m.—a small but telling marker of stability, continuity, and infrastructure rooted firmly in a place that outsiders might otherwise mistake for a remote construction front.

That social fabric was punctured on February 10, when John Charles “Jack” Davis died at the West Portal. Born in April 1880 in Osborne County, Kansas, Davis had taken supervisory work at the western end of the tunnel. Family testimony holds that he was inspecting timbering inside the bore when he was struck or injured. That scenario fits the known hazards of underground work, yet the contemporary record is nearly silent. No detailed news report has surfaced to confirm the mechanism of death. Instead, all that appears publicly is a sparse mortuary line, “Died—Davis, John Davis, at West Portal, Colo. Remains at Horan & Son funeral chapel. Funeral notice later.” For a project whose accidents had become part of a statewide conversation about cost, risk, and delay, that silence stands out. The historian must therefore treat each possible explanation as a hypothesis rather than a conclusion: the cause could have been medical rather than industrial; the contractor may have categorized the event as routine; or notice of the incident may survive only in lost or inaccessible newspapers. What we do know with reasonable confidence is that Horan & Son transported Davis to Denver before he was buried in the Elks Rest section of Sunnyside Cemetery in Victor, Colorado. Interment there strongly implies—though it does not conclusively prove—Elks affiliation, likely through the Victor lodge. Fraternal networks often handled death logistics internally, which may explain the absence of fuller obituary treatment in the press. His sinking grave marker, the thin archival footprint, and the weight of family memory together reveal how easily the life of a man working beneath the Continental Divide can drift toward the margins unless someone insists on preserving the fragments. (More on Davis and many other fatalities related to the Moffat Tunnel project can be viewed on our website.)

Two newspapers dated February 12 and 19 described major Elks events at the West Portal almost immediately after Davis’s burial in the Elks Rest section. Those reports record a large initiation and banquet, nearly ninety attendees, and the use of the local recreation hall for ceremonies. Whether the events were scheduled in advance or continued out of necessity, they unfolded only days after a death tied to the same workplace. The proximity is striking. Rather than pausing in the wake of loss, fraternal ritual continued openly, almost defiantly, at the logistical center of the project. Work, risk, grief, and social life had become tightly braided threads.

Another death in February 1926 tested the limits of institutional safety and later memory. Forest N. Snow was working inside the East Portal when a blast went off ahead of him. Both early reports and the Colorado Bureau of Mines investigation state that Snow and his partner, Tom Burke, returned toward the heading too soon and chose to walk back through the main bore rather than use the crosscut into the pioneer bore where fresh air was being forced. Snow collapsed after entering the gas-filled zone; Burke, though affected, survived and attempted rescue. The Bureau classified the incident as accidental asphyxiation caused by a violation of standing safety orders. In doing so, investigators wrote that the men had “deliberately” ignored the rule requiring use of the pioneer bore—language that, read in context, referred to a conscious decision to disregard instructions, not intent to die. That interpretation held at the time. Only in April 1928, well after the tunnel opened, did a lone retrospective account recast the event as suicide. That late claim collapses under scrutiny. Snow had a partner with him, the method offered no certainty of death, and the official investigation—conducted with immediate access to witnesses and tunnel rules—found no evidence of self-harm. Snow’s body went unclaimed at the morgue, and its final disposition remains unknown, but the historical record, when weighed by both proximity and evidentiary strength, resolves firmly back to accidental death.

Even in the midst of tragedy, the tunnel entered the national imagination. The film In the Heart of the Rockies included images of men working in and around the East Portal, placing the project within a larger visual story about the modern West. A radio broadcast that reflected on the construction effort used the line, “There were giants in those days,” signaling how the project was being mythologized even while the work remained incomplete.

That same narrative impulse soon reached print at a national scale. In June 1926, Sunset Magazine managing editor Edward A. Vandeventer published “Boring Through the Backbone of the American Continent,” a feature-length account of the tunnel as it neared completion. He framed the project as both an engineering feat and a geographic correction to the intractable reality of the Front Range, where for more than two hundred miles no river had cut a natural rail route through the Continental Divide. Vandeventer wrote that the tunnel would eliminate dozens of miles of four-percent grade over Rollins Pass. He understood Rollins Pass not as a fiasco, but as a costly proof-of-concept showing that winter made the mountain unconquerable from above, forcing the solution beneath it. His reporting was not abstract. Newspapers recorded his presence in Colorado, his time underground at the active headings, and his travel with resident engineer C. A. Betts. The tunnel in his account is not inevitable; it is precarious, still controversial, and financially strained. He emphasized that pairing the Moffat Tunnel with the proposed Dotsero cut-off would shorten the Denver–Salt Lake City line by 173 miles, possibly cutting six hours from schedules while recentering Denver on the national rail map. Even minor inconsistencies—such as variations in the spelling of his name in newspaper columns—hint at the urgency with which the story was being told. Two tunneling crews advanced toward each other through millions of tons of rock, with success to be measured, ultimately, not in miles gained, but inches missed.

February 1926 therefore exists at the intersection of progress reports, lived community, industrial hazard, and emerging myth. At West Portal, Elks ceremonies continued beneath winter sky and managerial oversight even as the men who worked below ground absorbed the risk. At East Portal, a split-second safety decision killed a worker and later invited distortion from a distance of years. And across the broader West, the tunnel increasingly appeared not merely as infrastructure but as a narrative—an audacious effort to correct geography itself. Contemporary rail reporting captured the practical benefit in stark terms. From Tabernash, three miles west of the tunnel, trains had previously needed fourteen to sixteen hours to reach Denver ninety miles away, requiring four locomotives to haul just twenty-two freight cars over the Divide. Once the tunnel opened, a single locomotive was expected to haul twenty-four cars from Tabernash to Denver in less than half that time. The promise was as concrete as it was transformative.

Taken together, the month reveals a paradox that defined the project at this stage. Under the mountain, the headings advanced methodically, supported by evolving safety systems that nevertheless failed at tragic moments. Outside the mountain, social bonds and fraternal ritual worked to stabilize a community living with constant risk. And beyond the mountain, the country began to imagine new maps made possible by a line bored straight through the Continental Divide. February 1926 was not yet a story of completion. It was the story of a gamble progressing toward resolution—its human cost increasingly visible, its technical achievement increasingly celebrated, and its ultimate meaning still being negotiated in real time.

This view shows the railroad bore at the East Portal of the Moffat Tunnel. The muck-train dumping track and pedestrian dock over accumulating icy water are visible, along with the chimney above the entrance, placed to vent fumes.

B. Travis Wright, MPS | Preserve Rollins Pass | February 4, 2026

The primary purpose of our work is to inform the public.

01Jan

January 1926: Two Deaths, One Survivor, and the Lease That Locked In the Tunnel

In Moffat Tunnel by Preserve Rollins Pass / January 1, 2026 / Comments are closed

January 1926 was the month the Moffat Tunnel kept moving forward even as its human cost could no longer be ignored.

Moffat Tunnel Construction Happenings from 100 Years Ago

Late Saturday night, January 2, 1926—technically it was just after midnight on Sunday, January 3—three track workers, Peter Giacomelli, Dan Metroff, and Frank Christian, were deep inside the pioneer tunnel at the East Portal of the Moffat Tunnel when a scheduled dynamite blast in the main heading went off as expected. They had seen the familiar warning lights that told them the explosion was coming, and under normal conditions that mattered, because a canvas bulkhead separating the pioneer bore from the main workings was supposed to hold back the blast fumes long enough for the blowers to push fresh air ahead of the men. That temporary barrier was their only protection.

This time it failed. Whether “jerked aside,” “whipped by the force of the blast,” or “caught” on an obstruction, the news coverage converges on a single outcome: the bulkhead didn’t close, and explosive gases surged through crosscut No. 8 into the pioneer tunnel. The three workers were suddenly in a rising wave of toxic powder fumes, coughing, choking, and fighting to keep their footing, and they understood immediately what the failure meant. They had only one chance: reach the blowers and the cleaner air ahead. (Additional discussion of the blowers is included near the end of the article, where a substantially expanded caption provides further technical detail.)

For a brief stretch they pushed forward together through thickening fumes. Christian remained the strongest; the other two weakened first. As dizziness overtook them, Christian physically supported Giacomelli and Metroff, but eventually all three collapsed. Searchers entering the tunnel minutes later found them unconscious in the bore, overcome by the fumes the bulkhead should have held back, and rushed them to the tunnel mouth for emergency treatment. Giacomelli, age 21, died at 6:00am. Metroff died roughly two hours later. Christian, barely alive, was slipping toward the same fate.

What happened next became the subject of a medical retrospective printed about a year later. That article described how Dr. C. A. Sunderland, the East Portal physician, resorted to a then-extraordinary approach: he strapped an oxygen mask to the dying man and kept him breathing pure oxygen for more than six hours. At a time when prolonged oxygen therapy was still considered experimental, Sunderland’s decision was a deliberate gamble. According to the report, the patient revived and ultimately recovered, a result framed as an emerging milestone in medical practice. The timing, the number of victims, the mechanism of injury, and the fact that only one man survived all make clear that this retrospective describes Frank Christian, the sole survivor of the Giacomelli–Metroff accident. Indeed, an article published January 5, 1926 carried the headline “tunnel gas victim on way to recovery,” while the article reported that “Frank Christian… who was overcome by gas which caused the death of his two companions in the Moffat Tunnel late Saturday night, was reported to be on the road to recovery last night.”

Newspaper follow-ups tried to locate relatives, and those efforts pulled Denver’s street grid into a tragedy that had unfolded inside a remote bore. Metroff’s family could not be found. Giacomelli’s situation was more complex. Records linked him to a Denver boarding address—2134 California Street—and revealed he had married in September 1924. His wife had inexplicably vanished from the boarding house on December 29, telling her landlady she was leaving to join her husband at East Portal; four letters from him arrived afterward, suggesting he did not know she had gone. Giacomelli, who had begun tunnel work only days earlier on December 27, had spent much of his life with his aunt, Mrs. Mary Marcolina, now living with her son, Denver patrolman Otto P. Marcolina, at 2806 Clay Street. Another cousin, John P. Marcolina, worked as a mechanic for Colorado Iron and Metal and lived at 2614 West Ninth Avenue. The tunnel could take a man before the outside world even learned how to find his next of kin.

That human story arrived in January 1926 alongside a set of project-wide facts that made every incident harder to shrug off, because the tunnel had entered the phase where progress could be counted in finite, graspable distances. By this point in January 1926, the work was approximately three-quarters to four-fifths complete by footage, with slightly more than three-quarters of available funds expended, and close enough to breakthrough that the remaining distance was no longer measured in tens of thousands of feet. Semi-annual statements translated percentages into a concrete remainder, reporting that only 6,811 feet of rock remained to connect the headings of the water tunnel.

Work continued simultaneously from East Portal and West Portal, but conditions diverged in ways that shaped cost, pace, and risk. From the east, early construction benefited from hard rock, rapid drilling, and minimal timbering, allowing portions of the main tunnel to be cemented and effectively completed at an early stage. Engineers later marked a milestone when crews “crossed the hump,” completing excavation on the Atlantic slope of the Continental Divide and beginning the descent toward the Pacific side. That transition, however, coincided with escalating water incursions as the bore passed over the apex. Recurrent seams released flows ranging from 200 to 500 gallons per minute, flooding pilot bores, forcing temporary suspensions of work, and requiring four pumps to lift water back over the summit so gravity could carry it out through the portals.

At the west portal, water was less the story than soft, unstable ground. Nearly every foot required timbering, sometimes reinforced with iron beams and inspected daily to guard against slipping walls. Engineers compared these conditions to those encountered during construction of the St. Gotthard Tunnel, noting that progress there was more than a mile behind where it would have been had hard rock prevailed throughout. Even so, forecasts remained notably consistent. Commissioners and contractors repeatedly predicted the tunnel would be “holed through” in June or July 1926, with excavation of the railroad tunnel completed by December 1 and full railroad completion by January 1927, potentially six months ahead of contract time, even as the reporting candidly acknowledged delays from flooding and slower progress at West Portal.

Financially, the project was constrained but controlled. By January 7, total expenditures had reached $7.72 million out of aggregate receipts of roughly $10.8 million, with $3.56 million devoted directly to labor, supplies, and tunnel construction. Excavation costs for the water tunnel rose modestly—from $11.05 to $11.34 per cubic yard—yet remained well below the contractual upset price of $17, while the cost of railroad tunnel enlargement declined during the same period. Interest on bonds was substantial, but officials still pointed to cash on hand, material inventories, secured credit, and audited, bonded deposits as evidence that the work had not outrun institutional control.

The pressure point was not whether the mountain could be drilled and blasted. It was whether the tunnel’s full two-bore vision—rail plus water—would be carried to completion on the financial terms the commission had established. The long-pending lease of the Moffat Tunnel to the reorganized Moffat Road, executed in this period, was framed as the final financial step preceding reorganization of the railroad system and as the mechanism by which taxpayers would be removed from direct exposure. Under the agreement, the Denver & Salt Lake Railway Company would lease the railroad portion of the tunnel for fifty years, with an option for renewal for an additional forty-nine years. Total rental under the contract would exceed $16,000,000 and was described as sufficient to retire and pay interest on approximately two-thirds of the outstanding tunnel bonds. For the first sixteen years the railroad would pay $345,900 annually. Beginning in 1943 the payment would increase to $563,740, after which it would decline gradually until, following 1972, the annual rental would be reduced to $12,000, or such amount as might be required to cover the cost of maintaining the Tunnel District organization.

The lease was not merely about rent checks. In addition to rental, the railroad assumed responsibility for maintenance estimated at approximately $75,000 annually, and it was required to carry $1,000,000 insurance on the tunnel timbering, keep the tunnel in repair, and insure inflammable portions for full value, barring acts of God. The rental payments were treated as an operating expense and given preference over mortgage bonds, with termination available in the event of default. If the tunnel was not completed by 1928, the railroad retained the right to finish the bore and credit the cost against rental obligations. The contract included provisions for overruns, requiring the railroad to assume responsibility for up to an additional $1,000,000 in bonds or assessments, including interest, if completion costs exceeded estimates. It also established competitive guardrails: the Tunnel Commission agreed not to rent the railroad bore to any other person or corporation for a period of less than ten years without the consent of the Moffat Road; if full capacity was not used, additional leases could be made, but not under terms more favorable than those granted to the Moffat Road, and the lease permitted the railroad to sublet the tunnel to other railroads.

The commission’s logic was blunt: railroad rental would bear two-thirds of total cost, leaving the remaining one-third to be recovered through water-bore rental, which, once secured on that basis, would remove the entire bonded debt of the Moffat Tunnel District—more than $9,000,000—from district taxpayers, with Denver the principal contributor. Contemporary reporting noted that executing the lease effectively blocked the Denver Water Board’s effort to secure a reduction in the rental set for use of the water bore. The commission declined a request to reopen hearings on bond valuation, pointing back to its December 23 resolution; under that finding, water-tunnel rental for the next sixteen years would amount to $172,950 annually. City officials protested that figure as excessive, suggesting informally that $110,000 to $135,000 might be more appropriate, but submitted no formal alternative proposal.

Operationally, the lease was sold as a turning point for the railroad itself. Reorganization officials expressed confidence that operation through the tunnel would stabilize finances by eliminating the costly twenty-six-mile mountain route over Rollins Pass, where upkeep and winter closures had contributed heavily to prior receivership. While tunnel rental was expected to be little cheaper than maintaining the old route, it would eliminate severe grades and winter interruptions, reducing maximum grades to approximately two percent. The new Denver & Salt Lake Railway company, incorporated in Delaware and qualified to do business in Colorado, was positioned to succeed the present Moffat Road once the technical steps of foreclosure were concluded, with final reorganization expected within several months.

And still, beneath all this paper confidence, one strategic uncertainty remained: no water user had yet committed to renting the water tunnel at the commission’s established rate. Officials acknowledged that without such a tenant, the final segment of the water bore might never be completed, potentially stopping at the last crosscuts necessary for economical construction of the railroad tunnel, and releasing $600,000 earmarked for cementing, which makes the water bore’s fate look less like engineering destiny and more like a demand-driven decision disguised as inevitability.

This same month shows Denver making sure it would not be boxed in on water. By mid-January 1926, Denver’s dispute with the Fraser Sources Irrigation & Power Company had ceased to be a contest over priority and had become a matter of execution. Following the Department of the Interior’s grant of independent ditch and tunnel rights, the outcome of the federal lawsuit no longer carried the power to alter Denver’s position, and contemporary reporting described the city’s remaining role as that of a “spectator.” The article characterized the maneuver as a “coup carefully planned,” emphasizing secrecy to prevent procedural interference. It also identified an engineering disconnect: Fraser’s original filings were based on a proposed tunnel alignment several miles from the Moffat Tunnel and at a different elevation; the Moffat bore “as now located” had not been contemplated when those claims were made. Denver’s approved ditch lines ran at a lower elevation, opening drainage acreage beyond the reach of the private system and eliminating functional overlap. Financial and administrative weaknesses further weakened Fraser’s posture, including failure to pay state corporate taxes, inability to demonstrate capacity to build, and a history of trying to sell its claimed rights to Denver, first at six figures and later for less. In this telling, Denver abandoned its push for immediate trial only once it was certain federal construction rights would be granted, and consent to continuance followed that assurance, not before it.

Across Colorado, January’s coverage kept looping back to symbolism, because the state’s Golden Jubilee coincided with repeated predictions that the Moffat Tunnel would be ‘holed through’ in 1926. Public confidence had matured into something both proud and exacting—support paired with an insistence on accountability and delivery. The tunnel was discussed as “just a question of time and money,” which reads as optimism until it is set beside the East Portal canvas bulkhead failure and the two bodies brought out at dawn.

Life at the portals was becoming civic as well as industrial. The East Portal Club was admitted into the Colorado Federation of Women’s Clubs as part of the state federation, and Mrs. Burgis Coy, the state chairman of literature, spoke at meetings about life at East Portal. That kind of organized, public-facing activity signals a camp trying to define itself as a place with routines, voices, and belonging, even while its daily purpose remained the same: feeding men and machinery into the mountain.

With “holing through” approaching, boosters began to plan how to turn breakthrough into a national stage. On January 27, 1926, coverage reported: “President Calvin Coolidge will press the button which starts the drill which will ‘hole through’ the Rocky Mountains in the Moffat tunnel next June [1926] if the plans of local and Denver men succeed.” The movement aimed to make the ceremony a national occasion, with news services and film companies carrying the story widely, and while some argued for postponing ceremonies until the first train ran through—estimated to be January 1927—the prevailing view favored midsummer, when the region could extract the greatest advertising value.

At the same time, writers revived an older reminder, “Although the tunnel has long been discussed as a railroad undertaking, it is worth recalling that its usefulness was never confined to rails alone. Five years ago the Boulder Daily Camera gave exclusive attention to the prospect of automobiles being carried through the bore on flat cars…” The point was not novelty, but authority and breadth: the law establishing the Moffat Tunnel Improvement District envisioned a transportation passage of broad public service, capable not only of accommodating trains but of carrying automobiles and other vehicles as conditions and operators might allow, with the western slope brought measurably nearer to Denver.

The project’s scale shows up in the work’s own arithmetic: thirteen pounds of powder to break a yard of ground, and two thousand, five hundred drills used daily. By early 1926, explosives were so central to modern infrastructure that the Bureau of Mines committed them to film in an educational motion picture, The Story of Dynamite, which included the Moffat Tunnel. Produced in cooperation with a major explosives manufacturer, it traced dynamite from raw material to finished cartridge, emphasizing precision, controlled heat, and methods intended to reduce accidental explosion. In its tunnel scenes, it showed gelatin dynamite in the driving of the Moffat Tunnel beneath the Divide, with safety sequences that demonstrated testing explosive strength with a ballistic pendulum and controlled detonations within steel galleries to assess dangers posed by gas or coal dust in mine atmospheres. Copies were made available without charge to schools, churches, civic organizations, and clubs through the Bureau of Mines, reflecting a belief that the public ought to understand not only dynamite’s power, but the disciplined methods required to use it. (For the segment showcasing the Moffat Tunnel in this film, see below or click here: https://www.youtube.com/watch?v=zMKZY7jCZH0).

January also carried a quieter export of Colorado experience. Percy L. Hamilton, a native of Moffat County born at his parents’ ranch near Craig—then part of Routt County—came to Golden in 1916 to attend the Colorado School of Mines, was initiated into Sigma Alpha Epsilon, left to join the U.S. Army during World War I, returned after the Armistice, then departed at the close of his junior year to enter professional work. He arrived at the West Portal shortly after construction commenced and remained from the earliest phases, including the initial surveys, rising rapidly through the ranks under Chief Engineer R. H. Keays from a mucker to become assistant superintendent for more than two years. Accounts emphasized his unusual ability to manage men and his willingness to share in the most dangerous work, with the repeated point that he never sent workers into hazardous ground conditions without being prepared to lead the way himself, a trait that earned esteem across lines of authority. By late 1925 or early 1926, Ulen & Company of New York secured a $25,000,000 contract to build a modern municipal waterworks system for Athens, Greece, expected to take about ten years; Keays was selected as chief engineer, and Hamilton was chosen as superintendent of construction. He accepted and was scheduled to sail from New York on January 16 under a reported five-year contract, working directly under Keays. His departure prompted a workforce tribute: a watch valued at $350, described in one account as diamond-studded, presented as a token of friendship and esteem, with writers noting that among roughly 450 men at West Portal, his promotion was greeted with pride tempered by regret, and that he was trusted by “the bosses and the men,” with the saying that “every man swears by Ham.” Before leaving overseas he visited his parents, Mr. and Mrs. Thomas Hamilton, pioneers of Moffat County, and stopped to see friends in Golden. His position at West Portal was filled by Thomas Williams, a Colorado mining engineer, preserving continuity as the drive continued. In time, that promotion would place Williams dangerously close to the risks the tunnel demanded.

Taken as a whole, January 1926 is coherent precisely because it refuses to separate the tunnel into tidy categories. A failed canvas bulkhead kills two men and nearly takes a third, while a doctor’s oxygen gamble becomes a retrospective “milestone” and a newspaper headline tries to reassure the public before the bodies are even fully accounted for. The project’s progress is translated into feet remaining, gallons per minute, timbered bad ground, and cubic-yard costs, while the financing is translated into rent schedules, insurance mandates, maintenance obligations, foreclosure mechanics, and an attempt to shift debt from taxpayers to users. Denver’s water strategy changes venue and posture, turning litigation into after-noise once federal authorization is secured. Civic life expands into the camps. A national celebration is planned, down to the imagined presidential button. The tunnel’s purpose is reasserted as broader than rail alone. Dynamite is harnessed, measured, tested, and distributed on film as public instruction. A West Portal leader takes Colorado’s hard-earned experience to Greece. Through it all, the month’s underlying logic stays the same: the closer the tunnel comes to completion, the less tolerance it has for anything going wrong, because every failure—mechanical, financial, political, or human—lands against a finish line that people are already treating as inevitable.

Blowers 3,500 Feet Inside the Moffat Tunnel


This photograph shows the blowers positioned roughly 3,500 feet into the mountain, and the geological conditions suggest that the location is East Portal, where the rock was particularly hard. From Hitchcock & Tinkler’s records: “Two Root, No. 5½ (18 in. x 36 in.), Style D, High Pressure Heavy Duty blowers at each end. These two blowers set up tandem in Water Tunnel, although the use of two at the same time is seldom required. Each is operated by a 100 H. P., 870 R. P. M., 3 phase, 60 cycle, 2,200-volt motor. Each blower has displacement of 16 cubic feet per revolution and when operating at 300 R. P. M. will deliver 4,320 cubic feet of air per minute against 4 pounds pressure, and designed to operate at any pressure up to 4½ pounds.

“The blowers are located back of a cross cut and a mine door erected just ahead, and are moved up as necessary, 12-inch ventilation pipe being used for discharge into headings. In addition, two fans, delivering 12,000 cubic feet of air at ½ ounce pressure are installed at blower stations. All ventilation pipe being furnished by The Thompson Manufacturing Co. of Denver, Colo.

“All cross cuts back of the blower station are bulkheaded. The low pressure fans discharge directly into the Water Tunnel at the mine door, and this induces an air current through the open cross cut and outward through the Railroad Tunnel.

“The air, as it moves rearward, swells the volume of the outward bound current, primarily caused by the fans, the Water Tunnel thus acting as an intake while the Railroad Tunnel functions as an exhaust for the ventilating system.

“This system of blowing, no exhaust being used, and first suggested by Mr. D. W. Brunton, Consulting Engineer, has proven a success in every way. After blasting in the headings the high pressure air is also used to quickly clear the headings and work is generally resumed after blasting in from 20 to 30 minutes.

“As the gases and smoke travel out and get into the larger Railroad Tunnel, it becomes diffused and diluted with the pure air, and becomes unobjectionable, especially as it passes a given point in a few minutes.

“The use of the high pressure air after shooting not only hastens the expulsion of the smoke and gases, but also cools the atmosphere for the workmen. The temperature of the Water Tunnel 3½ miles from portal being about 65 degrees, and when electric mucking machine is operating this temperature is increased about 10% due to heat generated by the motor.”

B. Travis Wright, MPS | Preserve Rollins Pass | January 1, 2026

The primary purpose of our work is to inform the public.

09Dec

December 1925: A Midnight Murder at West Portal of the Moffat Tunnel

In Moffat Tunnel by Preserve Rollins Pass / December 9, 2025 / Comments are closed

Heavy snow and deeper uncertainty made December 1925 the month when West Portal realized danger didn’t always come from the mountain.

Moffat Tunnel Construction Happenings from 100 Years Ago

December 1925 unfolded with a mix of anticipation and restraint, as if the year itself were holding its breath while Colorado looked toward the approaching breakthrough. Newspapers across the northwest interpreted the tunnel not simply as a piece of engineering work but as the instrument that would finally unlock the region’s potential. The Craig Empire captured this hope in its December 30th issue, insisting that “all Northwestern Colorado ever needed was transportation… with the building of the Western railroad and completion of the Moffat Tunnel, it will have transportation. Its farms will be reclaimed, its mines and oil fields opened, new enterprises of all kinds started, for transportation will open it to the markets of the world.” Communities were beginning to treat the tunnel’s impending completion as a turning point that would reorganize regional economics the moment trains could pass through the Continental Divide.

Yet the month’s actual progress figures did not match the scale of those expectations. East Portal entered the final days of December under heavy water flow—about 150 gallons per minute pouring into the pilot and railroad headings—requiring four pumps to operate around the clock. The water came from seams in the rock, but despite the volume, crews noted one saving grace: no timbering had been needed. The relative stability fit a broader truth about the east side of James Peak. There were fewer surface depressions, more pitch to the mountain, and fast snowmelt runoff, meaning fewer pockets where water could accumulate and percolate downward.

The west side behaved in the opposite manner. Engineers explained that every time the heading passed beneath a swamp or stream, soft ground followed. With more and deeper surface depressions, the West Portal became a collector of moisture, forcing the tunnel to contend with poor rock in zone after zone. Recent trouble was attributed by some to seepage from Fawn Creek, which may have been feeding downward along the slope. The last major obstacle still lay ahead: a branch of Ranch Creek—lying east of the Fawn Creek zone along the line of advance yet still part of the same west-side hydrologic regime—half a mile forward and 1,500 feet above the bore. The difficulty was serious enough that the contractors—Hitchcock and Tinkler—along with General Manager Lewis and Superintendent Kauffman, spent nearly all their time in the headings during December, guiding crews through what papers simply described as “treacherous ground.”

As the year closed, one newspaper offered a year-end snapshot of progress: the water tunnel stood at 14,220 feet from the east and 10,980 from the west, a total of 25,200 feet, reported as “seventy-eight percent completed”; the main headings were 14,200 feet east and 10,950 west, a total of roughly 25,150 feet, listed as “seventy-seven and nine-tenths percent completed”; and the railroad tunnel measured 11,600 feet east and 4,680 west, a combined 16,280 feet, said to be “fifty-one percent completed.”

While the numbers stalled, life around the portals continued in rhythms shaped by the season. Men left the camps in the days leading up to Christmas, thinning both portals as workers sought a brief return to their families. Some stories reflected the long arc of labor: Frank Beck, who had suffered a broken leg months earlier at the tunnel, had spent several months recuperating at home in Steamboat Springs. He returned to West Portal in early December, then left again to spend Christmas with his family before going straight back to work the following Sunday. Others captured the quieter continuity of community: on Christmas morning, Ernest Eugene Leist was born to Mr. and Mrs. William Leist, his father employed at East Portal; and on December 23, a marriage license was issued to Lawrence Pastorius and Marie Chidester, both of West Portal (they later divorced in 1938). Federal attention to the tunnel towns continued as well. In Christmas week, the U.S. Senate confirmed Vernet A. Kauffman to a four-year term as postmaster of West Portal, signaling that the settlement, however temporary it might appear on maps, mattered enough to receive formal civic appointments.

Not every December headline tied to the tunnel community was hopeful. In Denver, twelve-year-old Earl Frink was killed when a small tunnel in the backyard of the Tuckaway home at 1147 West Mississippi Avenue in Denver collapsed. Earl’s father worked at East Portal. Although the boy’s death was unrelated to the Moffat Tunnel project, the story landed with a particular ache because the circumstances suggest he may have been attempting to imitate the kind of work he saw shaping his father’s daily life—a tragic echo of the larger excavation unfolding under James Peak.

The month also brought movement on the political and economic architecture that would govern the tunnel once completed. The Moffat Tunnel Commission fixed rental values at two-thirds of the project’s total cost for the railroad tunnel and one-third for the water tunnel. The Denver & Salt Lake Railroad was the only applicant, though exclusivity was forbidden by law, guaranteeing eventual access to any other road that sought rights. At the same time, Denver continued its fight to control the water bore, armed with an Interior Department ruling that declared it more important to provide Denver with an adequate supply than to furnish water to the Fraser Sources Irrigation and Power Company. The ruling sharpened the stakes surrounding the water tunnel precisely because Denver’s own water use was immense—averaging 55,830,000 gallons per day in 1925, with a peak of 100,850,000 gallons on August 2, 1924, spread across 781 miles of mains and nearly four thousand hydrants. The water tunnel was increasingly understood as a future lifeline for a city already straining its existing system.

Gerald Hughes told the Denver Real Estate Exchange that the railroad would be fully reorganized and ready to run trains through the tunnel on the very first day the bore was completed. That confidence, however, glossed over the substantial operational, financial, and physical hurdles that still stood between aspiration and reality; the statement revealed more about the desire to project readiness than about the project’s actual condition.

It was in the midst of this combination of progress, pressure, and early-winter storms that West Portal—normally a predictable, work-worn settlement—was jolted by a crime so sudden and intimate that it briefly overshadowed the tunnel’s advance.


On a cold winter night in late December 1925, in a settlement carved out of snowdrifts and railroad ambitions, Fred Sperandio opened his back-room door to someone he seemed to know. A flicker of matchlight flashed against the cold timber. A single shot cracked through the dark. And by sunrise, the quiet community of West Portal—perched at the western mouth of the not-yet-completed Moffat Tunnel—had become the epicenter of a killing that baffled investigators, stirred fears among tunnel workers, and left a lasting mystery in the high country.

Newspaper accounts from Denver, Leadville, Fraser, and Colorado Springs scrambled to tell the story of the Italian immigrant who managed the recreation hall at West Portal and was struck down in the very room he lived in. Their coverage, uneven but earnest, paints a portrait of a man whose life was equal parts courage and conflict, and a crime scene that raised more questions than the bloodhounds, posses, or railroad guards could answer.

A LIFE LIVED IN THE HIGH COUNTRY

Fred Sperandio’s story begins far from Colorado. Born in Tyrol, Italy in 1887, he grew up “in the shadow of the Alps,” served in the Austrian army, and emigrated to the United States with his brother James in 1911. He worked mines in Trinidad, then Leadville, managing the Big Four mine with A. Seppi before moving to West Portal in 1921. There, he purchased a half interest in the recreation hall, a soft-drink and pool establishment that doubled as a social hub for tunnel workers.

Friends remembered him as adventurous, bold, faithful to those he trusted—yet also “reckless,” competitive, and adept enough at gambling to make money at it. Some said he was well liked and had no enemies. Others insisted he had collected a few. Both views were true. Sperandio could be generous and warm, but his fearlessness, his success at cards, and his habit of keeping cash on hand created undercurrents that did not always surface in polite company.

By December 1925, Sperandio lived in a small room at the back of the recreation hall, where he kept substantial sums from nightly receipts and private winnings hidden in secret caches. He knew the risks, but he had weathered worse in Europe’s mountains and Colorado’s mines. Confidence served him well—until the night it didn’t.

A KNOCK IN THE NIGHT

On Saturday, December 19th, Sperandio closed the hall near midnight and went to bed. Sometime after, a noise came from the alley door. Every version of the story agrees on the crucial detail: Sperandio rose, dressed at least enough to answer the door, struck a match to light his way, and opened the door to someone he recognized. Whether that visitor spoke to him or merely stepped forward is lost to history. What is not lost is the bullet, fired from a .45-caliber Colt automatic, that passed through his heart almost immediately. He died where he fell.

By morning, Edward Evans—the recreation hall’s day manager—arrived to open the place and found him on the floor. The room had been torn apart. Mattresses were slashed open. One showed signs of burning, as did parts of Sperandio’s clothing. The bed itself had been set alight. Someone had tried to burn the room or the body or both. The cash register had been emptied of roughly $125, but the real target had been the hidden money in Sperandio’s room, an amount somewhere between $1,500 and $1,800*. It was gone. (*In 2025 dollars, that amount translates to approximately $28,000–$33,000.)

CONFLICTING CLUES AND EARLY THEORIES

Grand County Sheriff Mark E. Fletcher and Deputy Sheriff James Quinn arrived from Hot Sulphur Springs, but the facts refused to resolve cleanly. Early reports floated the idea of two killers—one who hid inside the hall before closing and another who waited outside the sleeping quarters. Within forty-eight hours, however, Fletcher stated flatly that he now believed one man committed the murder, and that “clues unearthed” supported the theory that the killer was an acquaintance of Sperandio.

The sheriff’s reconstructed version of events—echoed by multiple Denver papers—held that Sperandio had been awakened by a noise at the rear door, had gotten up and dressed, and had stepped forward with a match in hand when the concealed robber fired. This version better matched the tight confines of the room, the single point of entry, and the precise shot. More importantly, it aligned with the inference that Sperandio would only open that door after midnight for someone he trusted.

The conflicting press portrayals of Fred’s personal life now took on new meaning. Some newspapers quoted locals saying he had “no enemies.” Others, relying on Leadville sources who had known him for years, admitted he had made a few. When weighed against the intimate nature of the killing and the deliberate effort to destroy evidence afterward, the latter assessment seems more convincing. The murderer did not stumble onto opportunity; he acted with knowledge—of Sperandio, of his routines, and of his hidden money.

SNOWBOUND MOUNTAINS AND A RACE AGAINST DISAPPEARING TRACKS

Snow had buried West Portal that week. Every report emphasizes the same reality: all roads were impassable, blanketed by gigantic drifts. Fletcher declared that escape by road was impossible, and he deployed men to watch the mountain passes in case the killer attempted to flee on snowshoes. The only viable escape route was the railroad.

Trains on the Moffat Road were carefully guarded. Passenger lists were checked. In one striking detail from a Denver story, officers discovered that a man who had boarded at West Portal was missing when the train reached Denver. No follow-up ever clarified who he was.

Recognizing the urgency, Fletcher summoned bloodhounds from the Quillen kennels in Colorado Springs. Their arrival on December 22nd produced the most tantalizing, if inconclusive, movement in the case. Released at the scene, the dogs ran directly toward the railroad, circling the depot and moaning when they lost the scent. Another paper reported that the dogs followed a trail from West Portal to Fraser, five miles away, before similarly losing it near the tracks.

Whether the dogs followed the same trail or different ones is impossible to know from surviving accounts. What is clear is that their work reinforced the sheriff’s belief that the killer moved toward the railroad—with or without boarding a train—and that his trace dissolved at or near the rail line.

Meanwhile, Sperandio’s brothers James and Charles arrived to assist. James returned to Denver with the body that evening; Charles remained to help the sheriff for several days.

A CRIME WITHOUT AN ENDING

By December 23rd, Fletcher stated publicly that an arrest was “entirely probable within the next few days.” Yet by the time the long obituary was printed in Leadville, no suspect had been named, no arrest had occurred, and no clear trail remained.

What survived was a portrait of a man whose life had been shaped by mountains in two portions of the globe; whose courage, charm, and intensity had won him both friends and enemies; and whose final moments were marked by trust, surprise, and violence.

It also left behind a mystery: whether his killer fled over snow, vanished onto a train, or simply blended back into the ranks of workers, gamblers, and itinerants who passed through West Portal that winter.

The newspapers closed the matter with a line as stark as tracks vanishing into blowing snow: “No trace of the murderer has been found.”

A century later, that remains the last official word.

Fred was unmarried and a member of the American Federation of Human Rights, an international co-Masonic lodge. He is buried in Evergreen Cemetery in Leadville, Colorado, in the IOOF section, a calm resting place that offers a measure of closure the investigation never found. His death appears on our list of Moffat Tunnel-era fatalities because it occurred within the West Portal settlement and arose directly from the conditions and community created by the tunnel project itself.


Set side by side, the two December narratives, the crews driving steadily through rock and water and the midnight violence that caught West Portal off guard, revealed a deeper truth about life at the portals in the winter of 1925. Men pushed toward breakthrough under the Divide, pumps fought the constant inflow, and Colorado’s optimism climbed with every foot gained, yet the same camp that kept the project alive carried risks that had nothing to do with geology. December 1925 was not simply another month of headings advanced; it underscored that the Moffat Tunnel was shaped by people who lived close to danger in all its forms. Workers, immigrants, gamblers, and wanderers shared a narrow world carved out of snow and timber, a world where the ground could shift in an instant, and in the shadow of James Peak the communities built to support a great ambition proved as unpredictable as the mountain itself. So the month closed with a peculiar duality. On paper, progress slowed to a crawl, held back by wet rock and the peculiar geology of the mountain, while in the public imagination the tunnel loomed larger than ever, an unfinished promise expected to reorganize markets, revive farms, open mines and oil fields, and bind Northwestern Colorado to the outside world in a way the region had waited on for decades. And as the year ended with only modest gains, the quiet that settled over the portals carried an unmistakable sense that the work waiting in 1926 would be anything but easy.

Image Caption #1: Fred Sperandio rests in Leadville’s Evergreen Cemetery, far from the snowbound doorway at West Portal where a single shot through the heart ended his life. The match he struck faded in seconds; the mystery of his 1925 murder has stayed cold for a century.

Image Caption #2: Published in newspapers in December 1925, this photograph survives today as an original print held by Preserve Rollins Pass from the Moffat Tunnel Commission archive. Of particular interest, the box positioned to the right of the mine cart tracks bears the label “POWDER.”

B. Travis Wright, MPS | Preserve Rollins Pass | December 9, 2025

The primary purpose of our work is to inform the public.

25Nov

November 1925: The Mountain Turns to Gravy

In Moffat Tunnel by Preserve Rollins Pass / November 25, 2025 / Comments are closed

Three-quarters complete and pressing westward, November 1925 forced crews to contend with the softest and most unpredictable ground encountered to date.

Moffat Tunnel Construction Happenings from 100 Years Ago

By November 1925, the Moffat Tunnel stood roughly three-quarters complete, with the main headings of both bores driven more than 23,000 feet beneath the Continental Divide. By late November, more than fourteen thousand feet of the railroad bore had been opened to its full 16-by-24-foot dimensions, representing roughly forty-six percent of the total length. On paper, progress looked steady; underground, the mountain had changed temperament. Ten thousand three hundred feet from the West Portal, crews struck the softest ground yet—a gray, water-laden material that behaved like newly mixed cement. Ordinary timbering bowed and splintered under the pressure, and progress slowed “almost to a crawl,” one engineer admitted, as workers resorted to dense breast-boarding and double sets of timber to hold back the mountain. Tunneling crews of the era often used food metaphors for soft, running ground; in 1925, the material under West Portal behaved with a heaviness and flow that a modern reader might picture as a kind of gravy.

At East Portal, 13,500 feet in, they faced a different obstacle: a heavy flow of sixty to eighty gallons a minute from fissures in a hard-rock seam, delaying progress by several feet a day. As the grade crested at the apex and began sloping down toward the western crews, gravity drainage would cease, and pumps might soon be needed to lift water back toward the apex so it could escape out the east side. For a time that November, the two ends of the tunnel labored under opposing forms of resistance—one collapsing, one flooding.

Even so, the pace of excavation impressed outside observers. The Moffat Tunnel Commission, led by W. P. Robinson, reported that 14,680 feet of the full-size railroad bore were complete—10,672 feet on the east, 4,213 on the west—and that crosscuts between the twin bores were seventy-seven percent finished. In the smaller water tunnel, engineers ambitiously expected the two headings to meet by January 1, 1926, with the main railroad headings connecting by July 1, 1926—six months ahead of schedule. If that held, trains might pass under the Divide before the contractual deadline of July 19, 1927. Still, the Commission cautioned newspapers against premature optimism. “Progress on the Moffat Tunnel is very satisfactory,” the official statement read, “but some papers have been led into an error as to the probable time of completion.” The reminder was deliberate: “All this is predicated upon fairly good ground at the west portal, but this remains bad.”

The local press captured both the strain and the spirit of the work. The Rocky Mountain News reported that west-side crews had struck ‘rock disintegrated by water and pressure… of the same consistency as newly mixed concrete,’ with forces ‘exceeding the heavy rock pressures already passed in the bore’ and ‘sufficient to crush ordinary timbers to bits.’ Other reports the same week described the pressure as strong enough to ‘break ordinary timbering like match sticks,’ underscoring the severity of the ground conditions at West Portal. Engineers added that progress had slowed “almost to a crawl,” as pressures in this zone surpassed those encountered “from the portal to the breasts of the bore,” requiring extra timbering beyond what ordinarily held the ground. In contrast, the Steamboat Sentinel and Herald Democrat focused on the eastern crews who had passed the tunnel’s high point and begun working downgrade toward the west—an engineering milestone that meant every new foot brought the two sides measurably closer. For the first time, both portal crews were advancing on the same side of the Continental Divide: the Divide had been crossed underground.

Thanksgiving brought a different kind of relief. At West Portal, two hundred fifty men and visitors crowded into the camp hall for an “athletic smoker”—a boxing event that pitted the tunnel’s two sides against each other in sport rather than in production. West Portal won two decisions, two draws, and a knockout; East Portal earned two draws of its own. The following week, newspaper columns filled with small human notes: R. J. (or Guy J.) Tanner, a veteran drill operator described as “one of the best,” returned to Boulder to spend the holiday with his parents. Roy Gordon traveled from the tunnel to Greeley to be with family. In Denver, a short notice recorded that Frank Beck appeared before the State Industrial Commission to seek compensation for the loss of his foot in a cave-in the previous December at West Portal. There were also marriages—Clarence Quick of East Portal to Ethel Knowles of Hutchinson, Kansas, and Arthur Brown of East Portal to Mildred Smith of Denver. In these glimpses from scattered papers, one sees the rhythm of a community living within an industrial epic: weddings, injuries, homecomings, and prizefights conducted under a mountain that still threatened to collapse.

Late in the month, the Commission turned from ground pressure to paperwork. On November 26, filings were made with the U.S. General Land Office for the formal railroad rights-of-way at both portals—1.77 miles at the west and 0.21 mile at the east. The request required the approval of Secretary of the Interior Hubert Work. Attorney Erskine Myer explained that the filings merely extended existing rights-of-way across federal land in the Arapaho and Colorado National Forests and did not affect private property already deeded to the Commission. The U.S. Forest Service had granted permission to clear timber along the corridors. Such quiet administrative steps rarely made headlines, yet they would determine how trains would legally reach both portals when the bore was finished.

By the close of November 1925, the figures told a story of both triumph and tension: 23,500 feet driven in the main headings, 14,000 feet enlarged to full size, and the Divide’s internal high point crossed from east to west. The crews were entering their third winter under the mountain, now armed with experience as well as ambition. The public saw a clean statistic—seventy-five percent complete—but the men underground saw something different: timbers bending, drills stalling, the hiss of water in darkness, and the small warmth of Thanksgiving light at the portal.

If October had been a month of acceleration, November was one of reckoning. The mountain had revealed its softest core just as the tunnel neared its hardest test. Each foot gained that month demanded new invention, new caution, and new faith that the opposite heading was still on line. The work continued, measured not only in feet of progress but in proof that endurance, not optimism, would carry Colorado through the last quarter of the Divide.

Image Caption #1: With the surrounding ground exerting pressure “sufficient to break ordinary timbering like match sticks,” workers in the pioneer bore labored under conditions that could change without warning.

Image Caption #2: Requiring extra timbering beyond what ordinarily held the ground, this section shows how progress slowed to a crawl.

B. Travis Wright, MPS | Preserve Rollins Pass | November 25, 2025

The primary purpose of our work is to inform the public.

22Oct

October 1925: Breaking Records, Not Yet the Divide

In Moffat Tunnel by Preserve Rollins Pass / October 22, 2025 / Comments are closed

Seventy-one percent complete and months ahead of schedule, October 1925 tested how far determination could outrun terrain.

Moffat Tunnel Construction Happenings from 100 Years Ago

Exactly one hundred years ago this month, the Moffat Tunnel continued moving from vision to inevitability. By October 1925, engineers projected completion “four to six months ahead of time stipulated in the contract,” placing the finish line ambitiously close: December 1926. Newspapers began treating the tunnel less as an experiment and more as destiny.

“The record-breaking progress being made on the construction of the Moffat Tunnel and the certainty that it will be completed by December of next year,” reported the Routt County Sentinel, “is already causing an influx of new capital into Routt County, all Northwestern Colorado, and the Uintah Basin in Utah.” “There is no predicting the progress and growth that may ensue with the opening up of the Moffat Tunnel,” the paper continued. “Side by side with the revival of mining, which is really taking place, is coming a development of agriculture and industry.” Investors, farmers, and speculators saw the bore under the Continental Divide as the key to opening an isolated region. Steamboat Springs, the paper predicted, would soon host creameries, canneries, sawmills, smelters, and even a potato-chip factory—because, it insisted, “the best potatoes on earth grow here.” The optimism was bold, but the reasoning was practical: transportation had always been the barrier, and the tunnel was about to remove it.

Underground, progress matched the headlines. By late October, seventy-one percent of the total work was complete—seventy-three percent for crosscuts, forty-two percent for the full-size railroad bore. The east heading had reached 13,062 feet, directly beneath the Continental Divide near Rollins Pass; the west had advanced 9,954 feet. Crews had broken all known world records for tunnel driving, until the mountain reminded them who set the terms. Roughly 10,300 feet from the West Portal, officials announced that the softest rock yet encountered had been struck, while at the east end a flow of eighty gallons of water a minute slowed drilling. Both setbacks tested patience and slowed the pace, but neither stopped it.

Then weather joined the contest. On the 25th, a blizzard snapped the Public Service Company’s power line over the Divide, silencing compressors and lights until repairs were finished the next day. The line, fed from the Boulder Canyon hydraulic plant, had carried power over the mountains to West Portal; its loss underscored how fragile the link between progress and interruption could be. Yet even isolation had its antidotes. Each afternoon, the off-shift crews at West Portal crowded into the recreation hall, drawn by the crackle of KOA Radio carrying the World Series across the mountains. “This group, isolated on four sides by almost impenetrable mountain barriers, is believed to be the largest single assemblage of [nearly 500] radio-baseball fans [following] the Pittsburgh-Washington struggle for baseball supremacy over the Rocky Mountain broadcasting station.” Specially built electric scoreboards flashed every strike and run as loudspeakers relayed play-by-play reports from Pittsburgh and Washington. The setup—built with help from KOA and the Denver Express—allowed the miners to follow every inning in real time. For a workforce hemmed in by increasing snow and diminishing granite, the daily broadcast was more than just entertainment; it was proof that the world beyond the Divide still reached them.

Commerce and daily life were also taking shape around the project. W. H. Wood advertised timber, mining props, and ties for delivery to Idaho Springs or upper Clear Creek, noting his “good location for wood” at West Portal—an early sign that local suppliers were strategically positioned near the construction camps. And amid the noise of drills and the crackle of radio, life continued in quieter forms: James Hayward of West Portal and Margaret David of Denver filed for their marriage license in early October, bridging the distance between the mountain’s workforce and the city that would soon benefit from their labor.

Technical progress coincided with administrative cleanup. Secretary of the Interior Hubert Work finally approved the tunnel commission’s right-of-way filings—more than two years after digging began. The delay stemmed from a clerical error in 1923: one application had been filed for both the railroad and water bores, when federal law required separate submissions. With the corrected filings approved, attention turned to the project’s lingering legal gaps. The commission still lacked title to water rights west of the bore, meaning, as one official noted, “there will be no water to run through the water tunnel when it is completed.” Litigation over those rights—covering the Fraser River and its tributaries—continued in U.S. District Court. Both rights-of-way followed nearly the same six-mile course through Grand County, underscoring how closely rail and water ambitions were intertwined.

Meanwhile, engineers from across the country gathered in Denver for their semi-annual conference with the tunnel commission. J. Vipond Davies and J. Waldo Smith of New York joined D. W. Brunton and L. D. Blauvelt of Denver to review progress, assess geology, and verify cost projections. Their findings affirmed that, despite soft rock and water seepage, the tunnel remained on track for early completion.

The legal framework itself was also clarified that month. “It is set forth in the law under which the tunnel is being constructed,” officials reminded the press, “that the tunnel commission may not grant exclusive rights to use the tunnel or its approaches to any person or corporation, either public or private.” As of October 15, the Denver & Salt Lake Railroad—the Moffat Road—remained the only bidder to operate through the bore, while the City of Denver had filed its own application to carry water through the pilot or pioneer tunnel. The commission emphasized its financial model: “It is the plan to rent the tunnels at a rate sufficient to pay for the interest and retirement of the tunnel bonds…. Rental of the tunnels for an amount sufficient to retire and pay the interest on the bonds will mean that the cost of the tunnel will not fall back on property owners in the tunnel district.”

Denver’s water board, already planning ahead, calculated that diverting 100,000 acre-feet of western-slope water through the pilot bore would require an initial outlay of $2,335,000 just to deliver the water to the West Portal—figures that gave scale to the city’s long-term transmountain ambitions. At the same time, the Oak Creek Times pointed out that once completed, the tunnel would eliminate the “excess grades by way of Corona,” allowing regional coal to move east at competitive cost. For the coal miners of Routt County, that was more than progress; it was survival.

Historian Marshall Sprague once observed that mountain passes act as “Great Gates,” funneling humans and animals across the relatively lower crossings of the Continental Divide, such as Rollins Pass. The Moffat Tunnel would break that pattern. Here, the physical landscape of this part of Colorado would no longer follow the mountain’s course—it would defy it. Water and snowmelt that once flowed toward the Pacific would be sent east toward the Atlantic watershed. Trains that once climbed the Divide would now pass through it. With the Moffat Tunnel, Colorado was beginning to rearrange nature itself—and its future.

October 1925 was a month when every discipline—engineering, finance, law, and labor—pushed forward together, sometimes awkwardly but always forward. Soft rock and snowstorms slowed the drills; legal errors and power outages interrupted momentum. Yet the work kept advancing, and belief in its purpose never wavered. Every headline—about soft rock, broken lines, or courtroom filings—was matched by the conviction that this work mattered. The mountain still dictated the tempo, but no longer the outcome; after all, Colorado was learning how to go through, not around, its obstacles.


Image Caption #1: The W.H. Wood Lumber & Supply Company was headquartered at West Portal, near the present-day entrance to Rollins Pass West.


Image Caption #2: Wet, heavy ground impeded the teams’ progress at West Portal. Several details in this photograph warrant attention: Multiple streams of water pour from the tunnel ceiling, their impact on the puddle below sending droplets upward—evidence of the steady, relentless seepage inside the bore. The worker standing in the mid-ground wears a hat, jacket, and trousers soaked through, underscoring just how saturated the working environment was.

B. Travis Wright, MPS | Preserve Rollins Pass | October 22, 2025

The primary purpose of our work is to inform the public.

29Sep

September 1925: Promises on Paper, Realities in Rock

In Moffat Tunnel by Preserve Rollins Pass / September 29, 2025 / Comments are closed

Optimism, obituaries, settlers, and lawsuits marked September 1925, as the tunnel was cast as Colorado’s gateway to prosperity even while danger stalked the portals

Moffat Tunnel Construction Happenings from 100 Years Ago

In September of 1925, life at West Portal looked deceptively ordinary. The local papers carried advertisements for Harry Credille’s services as a notary public, directing readers to the Recreation Hall—a single building that was equal parts post office, barber shop, store, and social hub. On the surface, it was civic life at its most routine. But just outside its doors, the month’s events revealed how precarious, and how ambitious, this community really was.

Recruitment notices shouted for attention in the same columns that carried Credille’s ads. They didn’t read like simple help-wanted ads; they had the urgency of a call to arms: “The Moffat Tunnel commission right now needs a hundred men, machine men, timber men, and muckers. Good wages are being offered with splendid working conditions.” Machine men could count on $5.50 a day, plus a footage-based bonus that reached $133 at West Portal in July, and $159 at East Portal. The fine print mattered: preference went to taxpayers in the district, a reminder that the tunnel was not just a public works project, but a political promise made tangible. By September, eight hundred men wore the Commission’s badge—five hundred at West Portal, three hundred at East Portal—two crews grinding toward one another through the granite heart of the Divide.

That many men in one place meant constant reminders of risk. Early in the month, superintendent John Henry Nicholls, fifty-seven, died of pneumonia after serving since “last winter” and working until “two months ago.” Soon after, a scaler, reported as William Geimer, age thirty-two, was crushed instantly when a ton of rock fell in the main railroad bore. His task had been to follow the dynamiters, prying loose any fragments still clinging to the roof. Burial records quietly corrected the newspaper account: his name was William M. Giener, thirty-three, survived by his wife and three small children at East Portal. Those discrepancies—Geimer versus Giener, thirty-two versus thirty-three—show how easily the record could slip when tragedy outran accuracy, and why it has taken long, patient research, line by line and record by record, to restore each man’s name and return him to his rightful place in history.

While funerals were held, headlines in Denver painted a different picture. “The Future of Colorado As Seen Thru [sic] the Moffat Tunnel.” “N.W. Colorado Has Dairy Future.” “Future of Colorado is Rosy.” At the Chamber of Commerce, more than a hundred realtors cheered the tunnel as a gateway to prosperity. At a manufacturers’ convention, two hundred delegates from “practically every city in Colorado” predicted a fifty percent surge in exports and suggested the state might rival Wisconsin in dairying. The Routt County Sentinel focused on the local harvest: sheep, vegetables, potatoes—all poised to reach markets once freight rates dropped. To read the papers that September was to believe that the tunnel’s concrete lining would harden into an economic revolution.

The optimism found its theater at fairs across Colorado’s northwest. Booths bore the emblem “Northwestern Colorado, the Land of Opportunity,” complete with a miniature oil derrick spraying crude and thousands of tiny bottles handed out as souvenirs. On September 22, fifty women from the Colorado-Made Goods Club became the first all-female group to inspect the West Portal, a symbolic nod to the tunnel’s role in reshaping the state’s future. And colonization drives promised more than wages; they also promised land. Prospective settlers were offered round-trip tickets from Missouri River towns for one fare plus two dollars, to view farms advertised as the tunnel’s inheritance. “More settlers for the Moffat Tunnel territory!” the headlines declared, as if the bore itself were plowing the frontier.

Then came the stories of water, flowing as inevitably into the conversation as it would through the mountain. On September 28, the federal government filed suit against the Fraser Sources Irrigation and Power Company, accusing it of sitting idle on rights first granted in 1909. The goal was clear: clear the path for Denver to claim Fraser River water and send it through the pioneer bore to the eastern slope. Newspapers reminded readers of Colorado’s Constitution, Article XVI, Section 6: “The right to divert the unappropriated waters of any natural stream to beneficial uses shall never be denied.” What had begun as a railroad project was already being recast as a lifeline for a growing city.

Progress reports told a story of momentum, but geology refused to play along. By September, both the main heading and the water tunnel were said to be two-thirds complete, while the railroad bore stretched to thirty-six percent of its final length. Some speculated about finishing early. But the West Portal team continued to be in “treacherous rock,” alternating between firm stretches and talc streaks that collapsed into broken zones, requiring heavy timbering and grinding progress nearly to a halt. The newspapers carried boosterism; the miners carried timbers.

Even the tunnel’s memory was being engineered. It was announced that Edgar C. McMechen had begun work on the project’s official history, a tome meant to knit together David H. Moffat’s dream, the pioneers who first broke the high-country trails, and the crews whose sweat and lives were buying each forward foot.

And still, amid all the speeches and lawsuits and projections of prosperity, the place could feel like a frontier camp. One night, a masked bandit walked into the West Portal Recreation Hall, leveled his pistol, and ordered seventeen men to line up against the wall. Here is how The Steamboat Pilot told the story:

***

HARRY CREDILLE FOILED ROBBER AT WEST PORTAL

According to reports appearing in the Denver papers, Harry Credille, manager of the recreation hall at West Portal for Hitchcock & Tinkler, is a quick thinking and quick acting boy. According to the story a solitary masked bandit walked into the crowded recreation hall at West Portal Wednesday night, lined 17 men against the wall at the point of a gun, searched them individually, and while he was engrossed in frisking his victims Harry Credille, manager of the department, scooped up the day’s cash, ducked thru [sic] a door leading to the commissary and saved several hundred dollars from the robber.

Credille, who also is justice of the peace at the camp, secreted the money on the outside of the building and hastened to summon officers to the scene, but before their arrival the lone stick-up had finished his work and disappeared. A cursory search of the camp Wednesday night failed to disclose any trace of him, and a rigid investigation was in progress Thursday.

The rude frame building which houses the recreation hall, post office, store and barber shop was the scene of wild excitement following the stickup, and the 17 near-victims armed themselves with all manner of weapons to go in search of the bandit. The usual crowd of tunnel workers was in the recreation room before the bandit entered. Men were gathered about the card tables of the big room, and the click of billiard balls was heard frequently from the area occupied by the pool and billiard tables. A straggler or two stood at the bar behind which was Credille. A pall of tobacco smoke enveloped the scene.

The outer door near the southwest corner of the room opened and a gust of fresh air sent the smoke eddying about the room. No one paid any attention, for the pool players were busily engaged in their games, and those at the card tables were occupied. “Stick ’em up!” came the terse command from the newcomer. Card players at the nearest table looked up in surprise, then, after some confusion, complied with the order.

“Line up against that wall with your backs to the room,” the intruder ordered, brandishing his gun to indicate the wall near the door. A hush fell as the men shuffled to the wall and stood with their hands high above their heads. Credille, standing near the cash register, dropped from sight behind the counter, unseen by the bandit. Then, with one eye on the door by which he entered, the stickup man started a systematic search of the recreation seekers, going thru [sic] the pockets of [each] as cooly as tho[ugh] he were doing some ordinary daily routine task.

Credille, finding the bandit’s back turned to him began stealthily to remove currency and silver from the cash register and the drawer beneath the counter. Then, silently, he eased his way from the recreation hall into the storeroom beyond the adjacent partition. His task of searching the men completed, the bandit backed away from them, still pointing his gun in their direction, and found to his dismay that the cash register was devoid of money!

“A hell of a fine crowd, this is!” he grumbled as he started toward the door by which he had entered. “Now all of you face to your right, and be sure you keep your hands up and high, too, because I’m in about the right humor after this to plug somebody.”

Then, as the seventeen men faced from him, he yanked open the door and disappeared into the night.

***

That tableau: billiard balls clicking, tobacco smoke hanging thick, and a notary’s cash drawer whisked away under a gunman’s nose, tells September 1925 more clearly than any headline ever could. The headlines promised a Colorado built on dairies and potatoes, booming exports, and the lifeblood of water carried through the mountains. But at the portals, life still meant funerals and pneumonia, men battling treacherous rock, and the occasional stick-up in a smoke-stained wooden hall. In the end, the month reads like the tunnel itself: one end promising daylight, the other still deep in shadow.

B. Travis Wright, MPS | Preserve Rollins Pass | September 29, 2025

The primary purpose of our work is to inform the public.

23Aug

Halfway There, Hands in the Air: August 1925 at the Moffat Tunnel

In Moffat Tunnel by Preserve Rollins Pass / August 23, 2025 / Comments are closed

Resignations, robberies, dances, and deadlines defined August 1925, as the Moffat Tunnel reached its halfway point and drew attention far beyond Colorado

Moffat Tunnel Construction Happenings from 100 Years Ago

In August 1925, the resignation of R. H. Keays as chief engineer of the Moffat Tunnel was accepted by the tunnel commission at its organization meeting. His $10,000 salary ($184,598.86 in 2025 adjusted for inflation) reflected the significance of the role, but the commission noted that “George Lewis, general manager of the company, will go on building the tunnel, so there will be no delay and few mistakes, if any.” Keays’ resignation, effective September 1, came as he prepared to leave for Athens, Greece, to supervise construction of a municipal waterworks there under a contract held by Uhlin and Company of New York. When Lewis took over and entered his new office, he was met with flowers and cards from many friends and followers, including a placard that read in part: “Loyalty to the tunnel district, loyalty to the Moffat Tunnel commission, loyalty to those who have honestly carried on the actual work has been rewarded by your selection as the chief of construction on one of the most interesting and important railway highways in the world, namely, the Moffat Tunnel… You have faithfully carried out the commands of the great builder, David Moffat, who gave his life to put the city of Denver in its proper place in the sun. You shall receive from the employees at the East Portal loyalty and harmonious co-operation until the tunnel is finished.” The commission determined that the position of chief engineer would not be refilled; with surveys completed, two experienced resident engineers—Burgis G. Coy at East Portal and James F. Cohig at West Portal—would see the work through.

Crime was not absent from tunnel life that month. Early in August, twenty-four-year-old Robert Eaton, identified in newspapers as the “East Portal Thief,” was arrested for stealing a suit of clothes and a gold watch from the Moffat Tunnel workers’ camp where he had been employed. Eaton had been sought in several Colorado cities since June 29. Later that month, the so-called “West Portal Bandit” attempted to hold up the recreation hall. (The recreation hall included the pool hall and soft drink parlor.) Grand County deputies believed he was the same man who had robbed a Fraser pool hall, five miles west of West Portal, the week before—taking $400. At West Portal, the attempt failed when Harry Criddle, the recreation hall manager, reacted quickly. Criddle had placed the day’s receipts in a satchel and, hearing someone fumbling at the rear door, was confronted at the front by an unmasked man ordering the few inside to “stick ’em up!” Instead of complying, Criddle unlatched the back door and fled into the darkness with the day’s takings. The would-be bandit, realizing the robbery had failed, ran off. Many tunnel employees joined the pursuit, but it was believed he escaped in a car that sped away from camp; a large manhunt stretched as far as Berthoud Pass.

On August 16, George Ames, twenty-seven, pleaded guilty before United States Commissioner Robert E. Foot to charges of embezzling $1,300 in postal money order funds and falsifying records while serving as assistant postmaster at East Portal. The thefts allegedly occurred between June 1924 and July 15, 1925, the day Ames left the postal service to operate a hotel in Nederland. He surrendered to Denver police while post office inspectors searched for him, telling them he had lost the money gambling. The Boulder Daily Camera ran the blunt headline: “George Ames Has Quit Keeping Nederland Hotel to go to Penitentiary.”

Elsewhere, the rhythms of community life continued. For the upcoming Labor Day holiday, the West Portal baseball club planned to travel to East Portal for a game. West Portal reported that ‘large numbers of visitors these days… all are welcome.’ Optimism about the tunnel’s future was equally present in print: officials reaffirmed that the smaller bore would be finished by May 1, 1926, and the full tunnel by January 1, 1927. At East Portal, Chief Inspector Allen shouldered more than technical responsibility, also serving as justice of the peace—a role underscored by the fact that his father sat as Chief Justice of the Colorado Supreme Court. The commission reported a healthy cash balance of $4,738,790.62, a figure often highlighted in local papers as proof of steady oversight. Boulder Rotarians welcomed representatives from East Portal to describe tunnel progress and working methods over lunch, an appearance that blended civic pride with technical education. And in lighter columns, social notes recorded C. S. Williams of East Portal purchasing a Duplex touring car—a reminder that even amid engineering feats and financial reports, the tunnel camps were still places where people lived, worked, and sought a touch of modern comfort.

The Steamboat Pilot of August 12 reported that “splendid progress is now being made on the tunnel, for both headings are in solid rock, and some new records are being made,” with the bore fifty-six percent completed and “competition very keen” between East and West Portal crews.

At the West Portal on August 28, a fire broke out in one of the creosoting sheds, causing about $1,000 in damages. The blaze began in a vat of creosote used to preserve tunnel timbers, though the cause was not determined. Employees prevented the fire from spreading to other buildings. The previous night, the Moffat Tunnel Jubilee dance, managed by Harry Criddle, drew the largest crowd yet, with music by the California Harmony Girls “unparalleled for excellence and rhythm.” The event celebrated the halfway mark in tunnel construction and was followed by another performance in Granby.

Newspapers also heavily promoted The White Desert, starring Claire Windsor, Pat O’Malley, and Robert Frazer, based on the novel by Courtney R. Cooper and filmed “in the Moffat Tunnel Country” and billed in advertisements as “A Glorious Picture, Glorifying Glorious Colorado.” Ads promised “At the Top of the World! There brute passions are unleashed—Blizzard and Avalanche try men’s souls—a woman finds romance amidst perils of the untracked wastes. You’ll love this great snow film!” The film played at the Curran and Empress theaters, at West Portal, and in Tabernash, with some calling it “the most beautiful photography that has ever been presented on the silver screen.” The timing of these promotions was not incidental: by tying Hollywood spectacle to the tunnel’s halfway milestone, the film worked as a kind of publicity for the project itself, presenting it not only as an engineering effort but as part of Colorado’s larger identity.

Not all of August’s news was cause for celebration. At West Portal, fifty-seven-year-old John H. Nicholls, a respected mining man and superintendent, fell ill with pneumonia while overseeing the work. He never recovered. Because he was actively on site when sickness overtook him, his death is counted among the Moffat Tunnel’s fatalities—a reminder that danger wasn’t always a cave-in or an explosion, but sometimes the invisible threat of disease. Today, if you wander through Denver’s Fairmount Cemetery, you’ll find his resting spot in Block 80, Lot 24, Grave 4. His headstone marks not just a life ended, but the human cost carried in the shadows of Colorado’s greatest engineering ambition.

The tunnel also drew outside attention. Justice Austin E. Griffiths of Seattle, president of the provisional committee for Washington’s proposed thirty-mile Cascade Tunnel, spent two days at West Portal studying the work. He likened Washington’s geographic challenge to Colorado’s and predicted that “Denver and Colorado do not fully realize the value of the Moffat tunnel, and will not realize it until years after completion of the work.” He praised Lewis’s leadership, saying he had “found many new ways of combating unseen obstacles” and calling the organization “most fortunate” to have him in charge.

Finally, the commission faced its first legal threat. A. S. Dennis of San Francisco claimed to have invented the “Pioneer system” of driving tunnels and to hold a patent on it, demanding damages for its use in the Moffat Tunnel without his consent. Commission attorney Norton Montgomery confirmed Dennis had approached them two years prior seeking payment, but Montgomery saw no legal basis for compensation and told Dennis’s attorney they “might as well start suit.” Montgomery emphasized that even if damages were awarded, the funds voted for tunnel construction could not be used for such payments.

August 1925 revealed the contradictions of life along the Moffat Tunnel: bold engineering milestones were shadowed by sudden resignations, postal scandals, attempted robberies, and even a creosote fire. Yet, in the very same breath, there were dances to celebrate the halfway mark, a ballgame to look forward to, and even Hollywood swooping in to turn the “Moffat Tunnel Country” into a stage for romance and danger on the silver screen. With fifty-six percent of the bore already carved through solid rock and January 1927 etched into the public imagination as the finish line, the tunnel was more than a railway project—it was an epic in real time, equal parts Colorado’s ambition and the unpredictable, very human drama of those who lived and labored on its frontiers.

B. Travis Wright, MPS | Preserve Rollins Pass | August 23, 2025

The primary purpose of our work is to inform the public.

26Jul

Barbecue and Ballots at the Bore: July 1925

In Moffat Tunnel by Preserve Rollins Pass / July 26, 2025 / Comments are closed

Celebration, controversy, and engineering milestones converged at the Moffat Tunnel in July 1925—when the public showed up above and below ground.

Moffat Tunnel Construction Happenings from 100 Years Ago

In July 1925, the Moffat Tunnel stood at the intersection of spectacle and progress, celebration and scrutiny. As workers carved ever deeper into the granite beneath James Peak, Colorado’s largest public works project to date became a gathering point for thousands—and a political flashpoint in the battle over who would control its future.

On July 4, East Portal transformed into a massive amphitheater of civic pride, athletic competition, and open-air revelry. The West Portal baseball team trounced their East Portal rivals 10 to 3 before a crowd of thousands. The holiday celebration was as expansive as the tunnel itself: two ball games, auto, horse, burro, and foot races, and a full rodeo unfolded throughout the day. Earl Bryant of Nederland, competing in the bronco-busting contest, was thrown twice; the second time, the horse fell on him, leaving him bruised and sprained.

Feasting was just as grand. Three barbecued beeves, seven pigs, roast lamb, and two barrels of pressed ham were distributed freely. With celebrations stretching from morning to night, East Portal saw more than 20,000 visitors. “In addition to the hundreds of automobiles which were driven to the east opening of the bore, four special trains of ten cars each carried full loads of passengers over the Moffat Road.” One train of 18 coaches alone carried 2,200 people. The Denver-bound “special” left the Moffat Depot at 8 a.m., offering “a scenic trip en route” for a round-trip fare of $1.90. Roads between Nederland and Tolland were overwhelmed with traffic, blocked for nearly two hours by the crush of cars—an early sign of the area’s popularity outpacing its infrastructure.

Meanwhile, at the more remote West Portal, over 600 visitors gathered for their own celebration, including a “Hard Time Barn Dance” the night before to benefit the West Portal baseball team.

For tunnel workers, July 4 was their sole holiday of the year. It was also the only time the public was allowed underground. More than 4,000 visitors entered the pioneer bore and exited through the wider railroad tunnel, granted rare access to the dark interior of the mountain. Some were struck by the contrast: “There was a silence like that in some lonely cathedral,” one visitor noted. “It was so dark that they could not see their hands before their faces.”

The evening concluded with an elaborate fireworks display.

Work resumed on July 5 with renewed intensity. According to Moffat Tunnel Commission president William P. Robinson, the tunnel was 56 percent complete as of July 1. Just days later, the water tunnel had reached 19,153 feet (60%), the main heading 18,331 feet (57%), and the full-sized bore 9,312 feet (29%). The tunnel was advancing beneath James Peak at nearly fifty feet a day. “Three crews were engaged in work at the East Portal during the ten days from July 10 to 20 and averaged progress of twenty-five and one-half feet a day… while at West Portal in this period the rates were twenty-two feet in each heading.”

On July 12, The Rocky Mountain News reported: “Previous world’s records set in the driving of the Moffat tunnel were shattered during the twenty-four hours preceding yesterday noon when a total advance of 104 feet in the four tunnel headings was reported.” Rock removal costs remained well below projections—$11.05 per cubic yard, compared to the contractor’s original estimate of $17. With speed came efficiency, and with both came public pride.

That pride was tested by politics. In mid-July, voters were asked to decide whether to recall the very commissioners driving the tunnel toward completion. The so-called Moffat Tunnel Anti-Recall Association ran newspaper ads urging voters to resist interference: “An attempt is being made to take the Moffat Tunnel out of the hands of competent men and place it in the hands of an organization held by the Supreme Court to be using ‘unlawful and illegal’ methods.”

That organization was the Ku Klux Klan, whose propaganda questioned both the engineering and the governance of the project. One pamphlet scoffed: “The Tunnel Act provides for but one tunnel — The Commission is digging three.” It insisted, incorrectly, that the water tunnel was both unnecessary and flawed: “The present tunnel commission have conceived the idea that three tunnels can be dug more cheaply than one. They claim that they must dig an unauthorized water tunnel in order to make cross cuts into the other small tunnel and keep the men at work. By means of an enlargement tunnel number two is to become the main tunnel. This plan entails three times the expense of the plan provided by law of digging one tunnel. The water is carried through the so-called water tunnel from the western slope to Denver. Water will not run uphill. Yet the eastern portal of the tunnel is one hundred feet higher than the western tunnel. The water must be forced through a 32,000 foot tube one hundred feet higher than the western portal of the tunnel. It is impossible to get a concrete tube 32,000 feet in length without some crevices and cracks in it. Under pressure these cracks will enlarge and tear away into large openings. The strain of the water pressure will wreck this long tube rending [sic] many engineers believe, the water tunnel useless. If the water tunnel is useless there will be no income from this source.”

The public disagreed.

On July 14, voters returned the entire Moffat Tunnel Commission to office. In the eastern division, the margin was nearly 400 to 1; in the west, roughly 4 to 1. The Eagle Valley Enterprise noted that “the klan was gloriously snowed under.” One editorial remarked on the sheer scope of engagement: “Ranchmen abandoned their work in the fields to go to the polls to register their protest against the attempt of the klan to capture the tunnel. The vote was surprisingly large.”

Following the election, commissioners Charles Leckenby and Charles N. Wheeler issued a joint statement:

“We are deeply appreciative of the splendid vote of confidence given us on Tuesday by the electors of this division of the Moffat Tunnel district. We are grateful that misstatements and falsehoods circulated on the eve of the election, which if true should condemn any official to everlasting oblivion, were taken for what they were worth and did not influence the result. To the scores of volunteer workers in every precinct, to the committees voluntarily formed, and to the individual voters, we are grateful. The vote of confidence will be a new inspiration to us to conduct this great work, so far as our part of it is concerned, with a mind single to the interests of the taxpayers, to speed coupled with economy, that transportation barriers may be broken down and our entire country prosper. And always bear in mind that there are no secrets in the operation of this great project. It belongs to the people; we never lose sight of the fact that we are servants of the people, intrusted with a great task and expending money that belongs to the people. As we have done in the past three years, so we will continue to do, give the very best ability and effort that is in us to the work you have intrusted to our care.”

Elsewhere, reminders of risk remained. In early July, The Colorado Transcript reported that John Beegle, father of Gage Beegle—the Mines student killed at the tunnel in June—traveled from Ohio to investigate his son’s death. Gage is buried in Galion, Ohio.

Prohibition violations continued at both portals. Joe Kisinger, age 22, a cook at East Portal, was found asleep in a stolen 1917 Ford near the Narrows. He had a half-pint of liquor on him. At West Portal, federal agents arrested James “Red” Evans, Elmer Petschauer, and Bud Shields for operating an illegal liquor business at the Eagle’s Nest Resort—also known as the Honky Tonk—located halfway between Fraser and the tunnel. Officers seized two gallons of whisky and hundreds of empty bottles.

In just one month, the Moffat Tunnel project achieved record-setting excavation, affirmed public oversight through the ballot box, and hosted the largest gathering in its short but storied history. More than 20,000 visitors came to celebrate, and over 4,000 descended into the bore—briefly trading summer sun for the dark hush of a cathedral-like void beneath the Continental Divide. When they emerged blinking into the light, they carried more than a souvenir: they carried a shared sense of direction. Beneath the granite, crews pressed forward. Above ground, Coloradans pushed back against fear and misinformation. And in July 1925, both the mountain and the movement proved unstoppable.

B. Travis Wright, MPS | Preserve Rollins Pass | July 26, 2025

The primary purpose of our work is to inform the public.

Preserve Rollins Pass background image